September will see John Holland continuing construction of the new vehicle underpass and Euroa Station Precinct upgrades.
Work being done:
• Piling and formwork for the new Handbury Street pedestrian underpass, new station platform, lift shafts, and Anderson Street vehicle underpass on the northern side of the rail corridor
• Construction and formation for new western rail track
• Construction of culvert and drainage
• Construction of new rail bridge at the northern end of project site
• Underground utility relocation in Anderson, Frost, and Handbury Streets
• Approved vegetation removal
• Deliveries of construction materials.
What can be expected:
• Works 7am-6pm Monday to Friday and 7am-1pm Saturdays
• A small section of Frost Street will be closed for approximately one week for utility relocation; resident access will be maintained
• Continued closure of Frost Street underpass with a pedestrian detour via the station platform
• All train services continuing via the eastern platform (Platform 1)
• Nearby residents may experience some noise and vibration.
How John Holland is managing impacts:
• Traffic management and reduced road speeds
• Wayfinding signage along pedestrian detour
• Environmental controls will be in place.
Machinery used:
Cranes, piling rigs, excavators, trucks, non-destructive digging trucks, earthmoving plant, compaction roller, cranes, jack hammers, and workers using hand tools and survey equipment.
Cancellation or extension of works:
Works can sometimes take longer than anticipated or can be cancelled at short notice and rescheduled.
Should this occur, impacted residents will be notified.
Talk to the team:
For any concerns, enquiries, or to book an appointment to talk to one of our team about these works, phone 1800 732 761, email inlandrailvic@inlandrail.com.au or visit Inland Rail’s shopfront at 46-50 Binney Street, Tuesdays at 10am-2pm.