A SECOND track possession last week allowed for some solid demolition works for the Inland Rail with large sections of the Anderson Street Bridge removed after a slight holdup due to the weather.
High winds on Monday 26 May saw the scheduled use of a 450 ton crane to remove the top deck of the bridge postponed by one day.
However, removal of the western track and delivery of 2.8km of new rail from P...